Ordering Concrete: Best Practices From Our Dispatch Desk

A smooth pour starts with a complete order. We need the right information to plan your trucks, so have it ready when you call, plan for the truck, and confirm your yardage before we load. Your concrete shows up on time, in the right amount, with the right mix.

Before You Call

Have This Ready

  • Job address, cross street and directions
  • On-site contact name and cell
  • Yardage (use our calculator)
  • What you’re pouring, and any QC or spec requirements
  • Placement: chute, pump or buggy
  • Start time
  • How long your crew needs to empty each truck
  • Account name or payment method
The Nicolia central dispatch board scheduling plants and mixers across Long Island
One dispatch board — the load batches at the plant nearest your job
Six Steps

Order Like a Pro

What our dispatchers wish every caller knew — from the first phone call to the last truck washing out.

I

Know Your Yardage

Use our concrete calculator and order a little extra. Running short mid-pour costs more than a little left over. Not sure? Give dispatch your dimensions and we’ll work it out with you.

II

Order the Right Mix

Tell dispatch what you’re pouring, not just “a load of concrete.” A footing, an interior slab and a driveway all call for different mixes.

  • Outdoor flatwork (driveways, patios, walks, steps): 4,000 psi with air entrainment. See our winter driveway guide.
  • QC or spec requirements? Just let us know. We handle them every day.
  • Need a higher slump? Ask for a water-reducing admixture instead of adding water on site.
  • Cold or hot weather: ask about heated water and non-chloride accelerator in winter, or a retarder in summer.
III

Plan for the Truck

Truck factMeasurement
Clear width needed, including mirrors9 feet
Chute reach from the rear bumper15 feet
  • Beyond 15 feet? Plan for a pump, buggies or wheelbarrows. We don’t run pumps, but we can recommend a pump company for your location and job.
  • Firm ground. Soft lawns, fresh fill and septic areas can swallow a loaded truck.
  • Existing pavement. A loaded truck can crack thin driveways, sidewalks and curbs.
  • Overhead. Check for wires, tree limbs and carports along the route.

Dispatcher tip: mention anything unusual when you call: a narrow street, a long backyard run, a gated community, or a site that needs a flagger.

IV

Schedule Smart

Dispatch ruleWhen
Need concrete on site at 8 AM or earlier?Call at least a couple of days ahead. First-round trucks book first, and this is strongly recommended.
Reserve your time slotThe day before, at minimum
Confirm your orderThe morning of the pour
Confirm your final yardageAt least 2 hours before you want it on site
Placements over 100 cubic yardsAt least 24 hours ahead
Off-shift work (nights, weekends, holidays)At least 72 hours’ notice
Lightweight aggregate concreteSpecial order. Call as early as possible.

The 2-hour yardage call is key. It lets dispatch load and schedule the right trucks, so you avoid cold joints and crews waiting on concrete.

  • Confirm the morning of. Every order is confirmed with dispatch the morning of the pour.
  • Truck spacing. Tell us how long your crew needs to empty each truck and we’ll space them to match. Trucks that sit get hot concrete. Trucks spaced too far apart risk cold joints.
  • Be ready at start time: forms set, inspection passed, crew on site.
V

Booking More Than One Pour?

Give dispatch each site, start time and yardage when you book — the day before at the latest — so every pour gets its own slot. If a morning job runs long or short, call right away and we’ll move your afternoon trucks.

Plans changed? Rainout, slipped inspection, early finish: call as soon as you know, so we can move trucks instead of having them wait.

VI

Have a Washout Spot Ready

This is required. The driver needs to wash off the chutes before heading back to the plant. Provide a washout area, or at least an empty wheelbarrow.

Questions

Frequently Asked Questions

Ordering
How do I order concrete?

Call dispatch at (631) 669-7000 with your job address, on-site contact, yardage, what you’re pouring and your start time. The checklist at the top of this page covers everything we’ll ask.

How much concrete do I need?

Use our concrete calculator and order a little extra. Running short mid-pour costs more than a little left over.

What mix do I need?

Tell us what you’re pouring and we’ll match the mix. For driveways, patios and walks, that’s 4,000 psi air-entrained concrete. If your job has QC or spec requirements, just let us know. We handle them every day.

Do you deliver small loads?

Yes. We deliver to homeowners and contractors across Long Island, from a small pad to a full foundation.

What areas do you deliver to?

Nassau County, Suffolk County and eastern Queens. For Brooklyn, western Queens and the rest of New York City, our sister company ELM Transit Mix serves you from Long Island City and Red Hook. See our locations.

Scheduling
How far ahead should I order concrete?

Reserve your time slot at least the day before. If you need concrete on site at 8 AM or earlier, call at least a couple of days ahead, because first-round trucks book first.

When do I need to confirm my yardage?

At least 2 hours before you want concrete on site. That lets dispatch load and schedule the right trucks, so you avoid cold joints and crews waiting on concrete.

How much notice do large pours need?

Placements over 100 cubic yards should be ordered at least 24 hours ahead. Lightweight aggregate concrete is special order, so call as early as possible.

Can you deliver at night or on weekends?

Yes. Off-shift work (nights, weekends and holidays) needs at least 72 hours’ notice so we can schedule drivers and plant crews.

Do I need to confirm my order on pour day?

Yes. Every order is confirmed with dispatch the morning of the pour, and final yardage is confirmed at least 2 hours before you want concrete on site.

Can I cancel or reschedule?

Yes. Call dispatch as early as you can. Once concrete is batched, it can’t be held.

Truck and Site
Will the concrete truck fit on my property?

Our mixer trucks need at least 9 feet of clear width, including the side mirrors, and firm ground. Soft lawns, fresh fill and thin driveways or sidewalks may not hold a loaded truck.

How far does the chute reach?

Our chutes reach 15 feet from the rear bumper. Beyond that, plan for a pump, buggies or wheelbarrows.

Do you offer concrete pumps?

We don’t run pumps, but we can recommend a pump company based on your location and job needs. Let dispatch know when you order and we’ll coordinate timing with them.

Pour Day
What do I need on site for the driver?

A place to wash out. The driver needs to wash off the chutes before heading back to the plant. Provide a washout area, or at least an empty wheelbarrow.

What if I need more concrete than I ordered?

Call dispatch right away with how much more you need, and we’ll get the next truck to you.

Can I pour concrete in winter?

Yes. Ask about heated water and non-chloride accelerator when you order. See our winter driveway guide.

More questions? See the full FAQ or call dispatch at (631) 669-7000. More guides: Protecting a new driveway from Long Island winters.

Ready to order?

Our dispatchers will walk you through your mix, yardage and timing.

Nicolia mixer feeding a concrete pump boom in the street beside a mid-rise apartment building
Mixer feeding a pump on a tight street — plan the access before the first truck rolls
View down a concrete pump boom at two Nicolia mixers feeding the pump on a narrow street between buildings
Two trucks and a pump on a tight street — seen from the top of the boom